Nama Plant Area (Caledonia) - Zambian Copperbelt (sitios de interés)

Descripción del sitio

screenhunter11jul231744.gif 
 
October 2, 2008:
Caledonia Awarded Mining Licences for Nama Cobalt Project
http://www.caledoniamining.com/pdfs/10022008b.pdf
 
 
Total Resource base:
Bodies "D": 63.91Mt at 0.08% Co, 0.035% Cu and 0.028% Ni
Bodies "A": 43.66Mt at 0.055% Co, 0.1% Cu and 0.028% Ni
Bodies "C": 78.22Mt at 0.043% Co, 0.012% Cu and 0.019% Ni
Total at 185.78Mt at 0.058% Co, 0.04% Cu and 0.02% Ni
(note that Production cost has been estimated below US$10/lb Co)
 
 
PROPOSED MINING & MATALLURGICAL OPERATION
• Straightforward, low cost, open pit mining method targeting production of 10,000    tonnes per annum (“tpa”) of   cobalt metal equivalent
• Capex Estimate for 10,000 tpa cobalt production~ US$ 200m*
• Production cost estimated below US$10/lb*
• Conventional drill & blast open pit, very low strip ratio, resource body exposed at surface
• Broken ore loaded by electric shovels directly into mobile crushers and conveyed out of the pit onto the overland conveyor
• 14 km overland conveyor discharged into coarse ore bins
• Vibrating plate feeder to conveyor feeding SAG mill and Ball mills
• Hydrometallurgical copper / cobalt extraction
• Roads & power line construction planned to commence third quarter 2008.
• Chinese fabricated plant and equipment will be delivered to site, installed and commissioned so that planned production can commence during first half of 2009
 
PROJECT STATUS 
• Chinese Feasibility Study on “A”, “C” and “D” underway, due Q3 ’08 with independent “Western” wrapper
• EIS approval from ECZ received for new access road and both power lines
• Conversion of retention licence into 25 year mining licences underway
• EIS submitted for mining & plant operations including “D”
• Negotiations with Chinese contractors, and plant and equipment suppliers close to finalization

PRIORITIES FOR 2008
• Finalize Feasibility Study & establish mine site, targeting production in 2009
• Sign additional off-take agreements up to 18,000t/yr of cobalt metal equivalent
• Finalize project funding
• Recruit dedicated project management team
• Continue drilling program, focusing on D1 depth extent & D north extensions & other identified targets and increase resources.
 
http://www.caledoniamining.com/pdfs/CALPres19052008.pdf
 
43-101 on Bodies "D" (May 1, 2008)
http://www.caledoniamining.com/pdfs/Nama-NI-43-101-08.pdf
 

Mapa del lugar de interés Nama Plant Area (Caledonia)

Panorámica interactiva con Google Street View

fotografía panorámica de Nama Plant Area (Caledonia), con el API de Google Street View

Mapas de contenido relacionado