Descripción del sitio
Other names: COP 'C'
RESOURCE BASE
Chingola "ACE" combined
Inferred: 35.56Mt at 1.54% Cu, 0.99AsCu
4.2.5 Other Satellite Deposits
Table 4-8 below shows the satellite pits resources in August 2005 owned by KCM but not included in the its LOM plan, which were based on an optimised US$1.00 per lb pit shell. These resources for Mimbula and Chingola Open Pit - ACE were based on alternative treatment options not practiced by KCM (ie heap leach) and had been classified as Inferred due to low geological confidence in the data used. Until a viable process method has been verified these resources can only be considered as future upside potential.