Deposits claimed by Collier in 1903 
Roan Selection Trust (RST) 1931-1969
Roan Copper Mines (RCM) 1969-1982
Zambia Consolidated Copper Mines (ZCCM) 1982-1998
 
NFC Africa Mining  Plc  (NFCA)
15% ZCCM Investment Holding Limited (ZCCM-IH)
85% China Nonferrous Metal Mining Co. Ltd (CNMC)
June 29, 1998
 
--------------------------------------------------------- 
 
ZAMBIA PRIVATISATION AGENCY
PRIVATISATION TRANSACTION SUMMARY SHEETS
zambia.gif
BIDS RECEIVED:
At bid closing, 28 February 1997, bids for Chambishi Mine were received from the following bidders:

- AUR Resources Inc, a company incorporated in Canada.
- Farrell Associates Group, composed of LMX Resources Limited, GMD Resources Corporation and Farrell Financial Limited, all Canadian incorporated companies.
- First Quantum Minerals Limited, a company incorporated in Canada.
- Sterlite Industries Limited, a company incorporated in India.

After consideration, the GRZ/ZCCM Privatisation Negotiating Team decided to reject all the bids that were submitted for the purchase of Chambishi Mine.
A Restricted Tender was then called and all the companies that had pre-qualified for the purchase of this package were invited to participate. Bids were finally received from the following bidders:

- China National Non Ferrous Metal Industry Corporation (CNNC), a company incorporated in the Peoples Republic of China.
- Farrell Associates Group who decided to re-bid through GMD Resources Corporation.
- Ivanhoe Capital PTE Limited, a Canadian registered financial development group with headquarters in Singapore
- Jet Cheer Development (Z) Limited, a company incorporated in Zambia.
- Sterlite Industries Limited, a company incorporated in India.

i) China National Non Ferrous Metal Industry Corporation (CNNC)
Descriptions Offer
Shareholding requested 85%
ZCCM retained interest (10% free, 5% repayable) 15%
Cash at close US$6 m
Deferred/conditional cash (@ 12% NPV) US$7.4 m
Feasibility commitment US$10 m

ii) GMD Resources Corporation
Descriptions Offer
Shareholding requested 60%
ZCCM retained interest (0% free, 40% repayable) 40%
Cash at close US$1.5 m
Deferred/conditional cash (@ 12% NPV) Nil
Feasibility commitment Not stated

iii) Ivanhoe Capital PTE Limited
Descriptions Offer
Shareholding requested 85%
ZCCM retained interest (0% free, 15% repayable) 15%*
Cash at close US$4 m
Deferred/conditional cash (@ 12% NPV) US$10.56 m
Feasibility commitment US$10 m
* Free carried for 4 years up to US$80 million capital investment.

iv) Jet Cheer Development (Z) Limited
Descriptions Offer
Shareholding requested 80%
ZCCM retained interest (20% free, 0% repayable) 20%
Cash at close US$8.5 m
Deferred/conditional cash (@ 12% NPV) US$4.92 m
Feasibility commitment US$10.4 m*
* Excluding US$2.6 m claimed to have been spent

v) Sterlite Industries (India) Limited
Descriptions Offer
Shareholding requested 80%
ZCCM retained interest (20% free, 0% repayable) 20%*
Cash at close US$7.5 m
Deferred/conditional cash (@ 12% NPV) US$11.61 m
Feasibility commitment US$10 m
* Free carried interest is only up to the first rights issue and thereafter no carry

SUCCESSFUL BIDDER:
China Non Ferrous Metals Industries Corporation (CNNC)

COMMERCIAL TERMS:
a) ZCCM retained interest (10% free, 5% repayable) 15%
b) Cash at close US$ 20 m
c) Deferred/conditional cash @ 12% NPV0 US$ 7.4 m
d) Feasibility commitment (over 3 year) US $ 10 m
e) conditional Investment commitment (over 5 years) US4110M

MAJOR PROVISIONS OF THE SALE AND PURCHASE AGREEMENT AND THE DEVELOPMENT AGREEMENT
- A commitment to invest a total of US$ 110 million in the development of Chambishi Mine during the first five years from close.
- a programme to re-establish Chambishi Mine in three (3) phases:
- Phase 1 Restore operations and achieve a production capacity of 3,000 tonnes of ore per day with the first 18 months from close;
- Phase 2 Increase production capacity to 6,000 tonnes of ore per day, after 30 months;
- Phase 3 Thereafter, endeavour to achieve a production capacity of 9,000 tonnes of ore per day, depending on the outcome of further exploration work on Chambishi West and South East ore bodies.
- A commitment to support local business development;
- A Human Resources development programme;
- Recognition of the Mineworkers' Union of Zambia.

THE PURCHASER:
China Non-Ferrous Metals Corporation of the Peoples' Republic of China
 
http://www.zpa.org.zm/trsum.pdf  (page 46)
 
 
 
logo_cnmc.jpg
China Nonferrous Metal Mining (Group) Co Ltd
 
CNMC boasts the most overseas nonferrous metal resources in China. At present, the projects both under development and operation include: Chambishi Copper Mine of Zambia, Tumurttin-Ovoo Zinc Mine of Mongolia, Tagaung Taung Nickel project of Myanmar, Thai-China lead-Antimony Alloy Plant, Mongolia Oyu Tolgoi Copper-Gold Project and so on... Chinese Investment Zone in Zambia centering around Chambishi copper mine is now being established.
http://www.cnmc.com.cn/en/jtjj/index.asp
 

Mapa del lugar de interés Chambishi Copper Mine Privatisation (NFCA CNMC)

Panorámica interactiva con Google Street View

fotografía panorámica de Chambishi Copper Mine Privatisation  (NFCA  CNMC), con el API de Google Street View

Mapas de contenido relacionado