The RT-2 Plant was intended to produce MOX-fuel elements and recovered uranium. The designed capacity of the plant is 1,500 tons of spent fuel per year, which means spent fuel reprocessing from the NPP of total 50–80 million kilowatts. The first facility of the plant is the spent nuclear fuel storage that was commissioned in 1985. The storage facility can receive and store 6,000 tons of spent fuel. The construction of the reprocessing plant itself started in 1984 but was halted in 1989 due to the lack of funding and public opposition. The RT-2 reprocessing plant will probably never be completed.